Attività svolte
- Welding piping prefabrication and erection - carbon steel
- Welding piping prefabrication and erection - stainless steel including pickling
- Tie-ins with existing plant
- Coating activities
- Painting activities
- Pressure test, blowing and drying activities
- Piping insulation
- Pre-commissioning activities