Part of Venture Global LNG. 18 mega modules in total, each made of 2 modules, built at the Baker Hughes yard in Avenza (Carrara, MS) for final installation in Louisiana, USA. ETI's scope covers 3 modules. Duration 18 months (Feb 2024 - Aug 2025). Per module: piping 182,000 kg (546,000 kg over 3), supports 9,000 kg (27,000 kg), valves 39,000 kg (117,000 kg), equipment 340,000 kg (1,020,000 kg). Welding 4,500 inches per module, 13,500 inches total; approx 5,600 inches welded as at the time of writing. Peak workload 60 resources. Indirect resources: Site Engineer, Quality Engineer, Construction and Site Manager, HSE.
Attività svolte
Erection of piping, equipment, valves and supports for 3 LNG mega modules
Piping 1/2" to 42", stainless steel and carbon steel